Printable checklist

BDA inspection checklist for building managers

Print it, tick it, file it with your BDA records. Items marked with a code reference come from the fire code or FCC rules. Items marked "suggested" are good practice from us, not a legal requirement.

Last verified Updated 5 sourcesChangelog

A clipboard checklist on an equipment closet shelf.
Set a free test reminder

Building details

Building name

Address

Fire marshal (AHJ) and phone

BDA permit number

BDA service vendor and phone

Monitoring company and phone

FCC booster ID (Class B)

Last annual test date

Next test due

Records on file

Monthly look

These are suggested checks for facilities staff. No code we cite requires them monthly, but each one catches a problem the annual test would otherwise find.

Before test day

Test day, stop by stop

What happens on BDA test day

What the tester does, what you do and what to have ready. Use the arrow keys to move between stops.

1. 2 weeks before

Book the tester and send the records

What happens. You book a tester your fire marshal approves, or one with the credentials it requires.

What you do. Send the tester the last annual report, the acceptance test gain values and a list of renovations, roof work and window replacements since the last test.

Have ready

NFPA 1225 20.3.10; IFC 510.5.3; IFC 510.5.4 item 6; IFC 510.6.1

2. Day before

Clear the way

What happens. Open trouble signals are fixed so they do not hide a real failure on test day.

What you do. Tell the monitoring company to expect BDA trouble signals during the battery test. Line up keys, cards and an escort for every area, and make the elevators available.

Have ready

Suggested; Miami-Dade requires access to all areas for its tests

3. Arrival

Walk the plan with the tester

What happens. The tester reviews the as-built drawings and the last report and confirms which areas need an escort.

What you do. Have the as-built drawings on hand and name one person who can open every door all day.

Have ready

IFC 510.4.2.7; NFPA 1225 20.3.10.1.3

4. Equipment room

Check the amplifier

What happens. The tester compares amplifier gain with the acceptance values, checks every active component against the manufacturer's specifications and looks for oscillation with a spectrum analyzer.

What you do. Open the BDA and battery cabinets. Keep the room clear; it should not be used for storage.

Have ready

IFC 510.6.1 items 2 and 4; IFC 510.5.4 items 6 and 7

5. Grid walk

Test every floor

What happens. A grid coverage test on every floor, 20 areas per floor, with a calibrated radio through the agency's system.

What you do. Keep the escort moving ahead of the tester so no floor is skipped for lack of a key.

Have ready

IFC 510.6.1 item 1; IFC 510.5.4

6. Critical areas

The places firefighters work from

What happens. The fire command center, pump room, exit stairs, elevators, elevator lobbies and standpipe and valve locations are tested to their higher standard.

What you do. Make sure each of these is unlocked and reachable, including the elevator cars.

Have ready

NFPA 1225 18.8.3

7. Radio check

Signal checks on the public safety system

What happens. Every radio system your fire marshal lists has to work in the building. Some fire departments check it themselves; Miami-Dade, for example, tests both its 450 MHz fire and 800 MHz police systems.

What you do. Ask your fire marshal's office ahead of time whether it will attend or wants its own test.

Have ready

MDFR General Guidelines for BDAs (Miami-Dade)

8. Battery and alarms

Prove it runs on backup

What happens. Batteries and power supplies are tested under load for at least 1 hour, longer if the battery shows signs of failure. Trouble and supervisory signals are confirmed at the fire alarm panel and the annunciator.

What you do. Watch the fire alarm panel with the tester and note every signal that comes in.

Have ready

IFC 510.6.1 item 3; signals per NFPA 1225 18.14 (suggested check)

9. Report and sign-off

Close it out on paper

What happens. The test is documented and signed by the approved tester, and the report goes to the fire code official.

What you do. Get the full written report with results per floor, gain readings and the battery test. Any failure gets a written repair scope and a retest date. File it, and set the next reminder.

Have ready

NFPA 1225 20.3.10; IFC 510.6.1

What the tester should do

The model fire code's annual test. Ask for each item to appear in the report.

A firefighter and a technician do a radio check in a stairwell.
Walk the stairs with the tester.

Test day

How the coverage grid is walked

Illustration
How the tester walks the coverage gridA floor plan divided into 20 test areas. A dotted route snakes through the center of every area, row by row. Nineteen areas pass and one fails, which the model code allows.StairElevators1234
  1. 20 roughly equal areasThe tester divides each floor into a grid and walks it, using a calibrated radio of the type the agency uses.IFC 510.5.4
  2. A test at each centerOne spot near the center stands for the whole area. Trying again a few feet away is not allowed.
  3. One failure allowedMore than one failed area fails the floor. With exactly two, the floor can be re-divided into 40 areas and passes with no more than two non-adjacent failures.IFC 510.5.4
  4. Critical areasStairs, elevators and elevator lobbies need 99 percent. General areas need 95 percent in the IFC and NFPA 1225; Miami-Dade uses 90.IFC 510.4.1; NFPA 1225 18.8.3, 18.8.4
The grid test from the model fire code. The pass and fail squares are an illustration, not a real building.Source: IFC 510.4.1, 510.5.4; NFPA 1225 (2022) 18.8.3, 18.8.4, A.20.3.10.

After the test

Signatures

Checked by (name, title)

Date

Tester (name, company)

Notes

Rules vary by state and county. Confirm what your fire marshal (AHJ) requires, and look up local rules on ERRCSCheck.

Free test reminder

Never miss the next BDA test

Add your building once and we email you before the next test is due. It is free, and setting a reminder never shares your details with an installer. Need a new system or a repair? Ask ERRCSCheck for up to 3 quotes.

Questions people ask

Is this checklist an official inspection form?

No. It is a working list for the building side. Your fire marshal may have its own annual test report form, and the tester's report is what gets submitted (IFC 510.6.1). Use this to make sure nothing is missed.

Can I save it as a PDF?

Yes. Use the Print button and choose "Save as PDF" as the printer. The site menu and footer are left off the printout.

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

  1. International Fire Code Section 510, Emergency Responder Communication Coverage, City of Eaton, Ohio (reproducing ICC model code text; edition not stated in the document)Verified October 25, 2026 · code
  2. NFPA 1225, Standard for Emergency Services Communications, 2022 Edition: Chapter 18 and section 20.3.10, Georgia Office of Insurance and Safety Fire Commissioner (reproducing NFPA text)Verified October 25, 2026 · standard
  3. 47 CFR 90.219, Use of signal boosters, Electronic Code of Federal RegulationsVerified October 25, 2026 · federal
  4. Florida Statutes 2026, section 633.202, subsection (18), The Florida SenateVerified October 25, 2026 · statute
  5. Two-Way Radio Communications Enhancement Systems: BDA Installation and Testing, Miami-Dade Fire RescueVerified October 25, 2026 · ahj document

Related

Set a free test reminder